Economical Hydraulic Jacking System for Tank Construion Machinery

Economical Hydraulic Jacking System for Tank  Construion Machinery

We are ready to provide complete solution for tank welding with different building method, equally bottom-to-best and leading-to-bottom tank construction, hydraulic lifting system are specifically designed for prime-to-bottom tank erection.

The subsequent short description provides the operating procedure in outline. It can in specific specifics be modified when required.
 
Step 1.  The tank base – plates are placed on the ready foundation and welded jointly.
Step two.  The beams or lattice function of the roof are assembled and lastly joined to the higher rim of the shell ring.
Step 3.  The jacking equipment is set up in the tank. The plates of the 2nd shell ring (subsequent to the best ring) are positioned outside the first 1.
Step4.   The accomplished portion of the tank (roof and top shell ring) is lifted hydraulically to a peak at which the plates of the 2nd ring can be moved into spot and the roof sheeting can be concluded.
Step5.   The plates of the 2nd shell ring are found specifically and welded collectively to the decrease edge of the very first ring.
Step6.   The plates of the 3rd shell ring are placed outdoors the 2nd shell ring.
Step7.   The concluded component of the tank (roof the two uppermost shell rings) is lifted.
Step8.   The over cycle of functions is recurring till the last (base) shell ring is finished.
Step9.    The total tank is lowered down to the base plate and welded to this.
Step10.  The lifting equipment is dismantled.

Economical Hydraulic Jacking System for Tank  Construion Machinery